At 80C Telok Blangah Street 31 we carried out a full HDB renovation for a homeowner between June and July 2026. The scope covered hacking, masonry, tiling and waterproofing, a new kitchen and bathrooms, electrical, air-conditioning, false ceiling and painting works, and custom carpentry throughout. Everything was done in line with HDB’s renovation permit requirements. This case study sets out what we did, the order we did it in, and the HDB rules that shaped each stage.
In this article
- 1. Project Overview
- 2. Scope of Renovation Works
- 3. How the Work Was Sequenced
- 4. The HDB Rules That Shaped This Job
- 5. Kitchen and Bathrooms
- 6. Living Spaces, Ceilings and Carpentry
- 7. Making Good, Testing and Handover
- Frequently Asked Questions
- Sources
| Project | 80C Telok Blangah St 31 renovation |
| Property | HDB flat (residential) |
| Client | HDB homeowner |
| Location | 80C Telok Blangah St 31, Singapore |
| Duration | June 2026 to July 2026 |
| Type of work | Full home renovation: building works, M&E, finishes and carpentry |
1. Project Overview
The homeowner wanted a complete refresh rather than a few spot repairs: a new kitchen, renovated bathrooms, new wiring and lighting, air-conditioning, and built-in storage in every room. On a job like this, most of the risk sits in sequencing. Wet works, concealed wiring and plumbing all have to be finished and tested before the ceilings, paint and carpentry close everything up. You can see the project summary and gallery on our 80C Telok Blangah project page.
2. Scope of Renovation Works
The documented scope of works for this home renovation was:
- Site preparation and protection; HDB permit and approval requirements
- Hacking and demolition; removal and disposal of existing finishes
- Masonry and partition works
- Floor and wall tiling, including screeding and grouting; waterproofing
- Kitchen and bathroom renovation; plumbing and sanitary modifications
- Electrical wiring, power points and lighting installation
- Air-conditioning and ACMV works; false ceiling works
- Painting and decorative finishes; doors and windows; aluminium and glass works
- Customised carpentry: kitchen cabinets, wardrobes, TV feature wall, storage cabinets and built-in furniture
- Loose furniture, sanitary fittings, kitchen fittings, grilles and metal works
- Final making-good, cleaning, debris removal, testing and completion to HDB requirements
3. How the Work Was Sequenced
- Permit and protection. We confirmed which items needed HDB approval, then protected the unit and common areas before any hacking began.
- Hacking and demolition. We removed the old finishes and disposed of the debris. This is “restricted” noisy work under HDB rules, so it was scheduled inside the permitted weekday hours.
- Masonry, screeding and waterproofing. We built the partitions, screeded the floors and laid waterproofing in the wet areas before any tiles went down.
- Concealed services. Electrical wiring, power points, plumbing and sanitary modifications, and air-conditioning piping were run while the walls and ceilings were still open.
- Tiling and ceilings. We laid the floor and wall tiles, grouted them, and installed the false ceilings and lighting points.
- Doors, windows, aluminium, glass and grilles. We fitted the openings and metal works.
- Painting and carpentry. We painted, then installed the kitchen cabinets, wardrobes, TV feature wall and storage. All of this was fitted after the dusty trades had finished.
- Fittings, testing and handover. We installed the sanitary and kitchen fittings and the household fixtures, made good, cleaned, tested, and handed over in July 2026.
4. The HDB Rules That Shaped This Job
Every HDB renovation runs under the same published rules. These are the ones that applied directly to the work at Telok Blangah:
- Registered contractor. HDB requires flat owners to engage only contractors from its Directory of Renovation Contractors (DRC). This applies even to works that do not need HDB’s approval (HDB: Important Information on Renovations). We are HDB Renovation Permit registered.
- Hacking needs approval. All demolition and hacking of walls, partial or complete, requires HDB’s prior written approval (HDB).
- Working hours. General renovation is allowed from 9am to 6pm on weekdays and Saturdays. Noisy works such as hacking, removing finishes and heavy drilling are limited to 9am to 5pm on weekdays only. No renovation is allowed on Sundays and public holidays (HDB).
- Waterproofing in bathrooms. HDB requires pre-packed waterproofing screed and a waterproofing membrane before new bathroom floor finishes are laid. The membrane must be upturned at least 150mm against the walls and kerbs (HDB: Renovation Guidelines for Building Works).
- Licensed trades. Water service and sanitary works must be done by a PUB Licensed Plumber, and electrical installation work by an electrical worker licensed by the Energy Market Authority (HDB: Application for a Renovation Permit).
- Air-conditioning. Air-conditioners in HDB flats must be installed by a BCA-trained condensing unit installer (HDB). Regulation 41B(2) of the Building Control Regulations 2003 allows only trained installers to fit units on a building’s exterior (BCA: Air-conditioning safety).
- Windows. Only BCA-approved window contractors listed with HDB may install or replace windows in HDB flats (HDB: Renovation Guidelines for Window Works).
| Work at 80C Telok Blangah | HDB / authority requirement |
|---|---|
| Hacking, demolition, removal of finishes | HDB approval for wall hacking; noisy works 9am–5pm on weekdays only |
| Bathroom floors and waterproofing | Waterproofing screed and membrane, 150mm minimum upturn |
| Plumbing and sanitary modifications | PUB Licensed Plumber |
| Electrical wiring, power points, lighting | EMA-licensed electrical worker |
| Air-conditioning installation | BCA-trained condensing unit installer |
| Doors, windows, aluminium and glass | Windows by BCA-approved window contractors listed with HDB |
5. Kitchen and Bathrooms
The kitchen was rebuilt with full-height dark cabinetry, a dark worktop, a white tiled backsplash and light floor tiles, all finished by our in-house carpentry team. In the bathroom we did the plumbing and sanitary modifications, waterproofing, white wall tiling with dark floor tiles, and new sanitary fittings and accessories. Sanitary pipes and fittings in black match the dark kitchen palette.


6. Living Spaces, Ceilings and Carpentry
Across the rooms we installed false ceilings with track lighting and a ceiling fan point, new floor finishes, and fresh paint. The carpentry package included kitchen cabinets, wardrobes, a TV feature wall, storage cabinets and other built-in furniture. Our carpentry uses E0-certified, formaldehyde-free wood. In the corridor, the built-in wardrobe runs the full height of the wall. After the carpentry, we fitted the doors, aluminium and glass works, grilles, loose furniture and household fixtures.


7. Making Good, Testing and Handover
The project closed with final making-good, cleaning and debris removal, followed by testing and completion to HDB requirements. The unit was handed over in July 2026. Each of our jobs runs on an itemised quotation and a delivery schedule written into the contract, with one project manager from start to finish.
Frequently Asked Questions
How long did the 80C Telok Blangah renovation take?
The works ran from June 2026 to July 2026, covering everything from site protection and hacking through to testing and handover.
Do I need an HDB permit to renovate my flat?
Some works do and some do not. Hacking of walls, for example, needs HDB’s prior written approval. Whatever the scope, HDB requires you to use a contractor from its Directory of Renovation Contractors, even for works that need no permit.
When can noisy renovation works be done in an HDB flat?
Noisy works such as hacking and heavy drilling are allowed only from 9am to 5pm on weekdays. They are not allowed on Saturdays, Sundays, public holidays or the eves of certain major festivals. General renovation is allowed from 9am to 6pm on weekdays and Saturdays.
Can I replace the bathroom tiles in a new HDB flat?
Not straight away. HDB does not allow the original toilet floor and wall finishes to be replaced for 3 years from the block’s completion date. You can lay new floor finishes over the existing ones using adhesives.
Who can install air-conditioners and windows in an HDB flat?
Air-conditioner condensing units must be installed by a BCA-trained installer. Windows must be installed or replaced by a BCA-approved window contractor listed with HDB.
Related reading: Bukit Batok West Ave 8 HDB renovation · What a renovation company in Singapore actually does · What to verify before hiring a renovation contractor · All projects
Sources
- HDB – Important Information on Renovations
- HDB – Renovation Guidelines for Building Works
- HDB – Application for a Renovation Permit
- HDB – Renovation Guidelines for Electrical Works
- HDB – Renovation Guidelines for Air Conditioner Installation Works
- HDB – Renovation Guidelines for Window Works
- BCA – Air-conditioning safety